Use of the Observational Method (Best Way Out) to Allow Driven Pile Installation in Chalk
Paul Morrison, Mike Tutt, Mike Ryan

This paper describes the design process, trial testing and contract pile installation of 772 precast concrete piles at a site in Surrey, South East England. Recommendations on how to improve the design, construction trials and mail contract piling phases of the project are made.


 article #874; publication #54 (AM-2000)